HEAP LEACH FACILITY – CIVIL WORKS

2023

Client: Norton Gold Fields

  • Cleared 4,500,000m2
  • Load, haul and placed 1,000,000m3 of material, i.e. storage ponds, leaching pads
  • Constructed 12km of haul roads
  • 60km HDPE piping
  • 500,000m2 HDPE lining
  • 0 LTIs
  • Works completed ahead of schedule
  • Works completed during COVID
  • 90% self perform
  • Works peaked at 110 persons onsite